Quick Summary
To track subcontractor costs on a renovation, build the budget from the sub's itemized quote, record every sub invoice in QuickBooks against that one job the day it arrives, and match each invoice line back to the quote before you pay it. Record homeowner money received before the work is done as a deposit, not income.
- Build the job budget from the sub's written, itemized quote.
- Match every invoice line to a quote line before paying it.
- Code each sub cost to the same job in QuickBooks.
- Treat homeowner money received early as a customer deposit until the work is done.
- File the invoice, estimate, and warranty with its end date in one project folder.
Table of Contents
Why Subcontractor Costs Slip Away on Renovation Jobs
To track subcontractor costs on a renovation, you need one job per project, one line per cost, and a habit of recording each invoice the day it arrives. Most renovation losses do not come from a bad price. They come from costs that land in a general pile and never get matched back to the job that caused them.
This guide is written for owners of high-end renovation and rehab companies that rebuild older homes for homeowners. The homeowner may pay you directly, or pay through a bank loan where the lender has a third party inspect the work and approve each draw. Either way, the books have to show what each job really cost.
Here is the core problem. A sub quotes the work, you pay a deposit, the work happens, and the final bill shows up weeks later. By then the job is finished in your head but not in your books. On HVAC work, equipment and duct runs often get billed together, and when nobody splits them apart, the costs blur.
Small leaks add up fast:
-
A sub deposit recorded as a general expense
-
Extra duct runs on the final invoice that never had a quote line
-
Warranty paperwork left in a truck instead of a project folder
-
Homeowner payments logged as income before the work is finished
Every one of these breaks the trail, and once the trail is broken you cannot tell whether the job made money.
Below, we follow one HVAC sub's cost from quote to warranty so you can adapt the process to your next job.
Build the Renovation Budget Before the Sub Starts
The budget comes first. A renovation budget is the line-by-line plan of what each phase should cost, split by trade, so every invoice later has a place to land.
Start with the phases you already know: demo, framing, HVAC, sheetrock, cabinets, paint. Under each phase, list the trade and the expected cost. For HVAC, that means equipment and duct work as separate lines, never one lump.
A simple structure works well:
-
Phase name
-
Trade or sub name
-
Quoted amount
-
Deposit expected
-
Final payment expected
If you run several job types, keep a separate budget template for each. A kitchen rehab and a full gut have different cost shapes, and mixing them hides the variance.
Watch out: a budget built from memory instead of the sub's written quote will not match the invoice later. Build it from paper.
For how job costs, draws, and billing stay connected across a whole project, see our construction bookkeeping for general contractors and builders.
Get the Sub's Itemized Quote and Tie It to One Job
One quote, one job, one folder. An itemized quote lists each piece of work with its own line and amount, and your whole cost trail hangs on it.
Ask the sub for the quote in writing with the pieces separated. For HVAC, you want equipment on one line and duct work priced per run on another. A quote that says "HVAC install, lump sum" tells you nothing when a higher final bill arrives.
When the quote comes in, do three things:
-
Save it to the project folder with the date
-
Add the amounts to that job's budget, not a general account
-
Note the payment terms, including any deposit
A common mistake is booking the quote as an expense. It is not an expense yet. It is a commitment, and it belongs in the job budget so you can compare it to actual bills later. If your QuickBooks plan supports purchase orders and project budgets, use them for this. If not, a budget tab in Excel with one row per quote line does the same job.
A Worked HVAC Example: Equipment Plus Duct Runs
This is a labeled hypothetical with round numbers, not a real job or a price guide. A homeowner approves an HVAC replacement on an older home. The sub's itemized quote shows:
| Line | Quantity | Rate | Quoted Amount |
|---|---|---|---|
| Equipment | 1 | $9,000.00 | $9,000.00 |
| Duct runs | 6 | $400.00 | $2,400.00 |
| Total quoted | $11,400.00 |
When the sub's invoice arrives, it shows 8 duct runs instead of 6:
| Line | Quoted | Invoiced | Variance |
|---|---|---|---|
| Equipment | $9,000.00 | $9,000.00 | $0.00 |
| Duct runs | $2,400.00 | $3,200.00 | $800.00 |
| Total | $11,400.00 | $12,200.00 | $800.00 |
Matching line by line shows the $800.00 variance at once. Two extra runs may be legitimate, for example if the crew found a problem behind a wall. The point is that you ask before you pay, and you decide whether the extra runs need a written change order or go back to the sub for a correction.
Equipment is a fixed purchase. Duct runs can grow when conditions are hidden. That is why the budget carries two lines instead of one. A lump-sum invoice paid without matching it to the quote lets extra runs through without anyone approving them.
If the scope changes mid-job, our guide to construction change-order tracking shows how to tie the new scope to costs and billing.
Two Ways to Set Up the Job in QuickBooks
There is more than one workable setup, and the right one depends on what you want to see in your reports. Two common approaches:
| Setup | How it works | Good fit when |
|---|---|---|
| Cost types as COGS accounts, job as a project | A set of COGS accounts by cost type, such as demo, HVAC, cabinets, and paint. Each job is its own project in QuickBooks. | You want to compare the same cost type across many jobs and see each job's total by project. |
| One COGS account per job | Each job has its own COGS account, and everything for that job posts there. | You mainly care about each job's total cost and want a simple chart of accounts for a few jobs at a time. |
With the first setup, a firm that tracks around three dozen cost types gets detail by trade on every job, at the price of more accounts to keep clean. With the second, the account list grows with every new job, and cost types are not separated unless you add a second tracking layer.
Neither is wrong. Pick the one that answers the questions you will actually ask, such as which trade ran over on the last four kitchens, or what a whole job cost. Once chosen, use it the same way on every job.
For a deeper setup walkthrough, see our QuickBooks job costing guide.
Deposits, Draws, and the Cash Gap
A sub often wants a deposit before work starts. That deposit may come out of your checking account or a credit card before any money from the homeowner or lender has arrived.
The gap between money out and money in is the cash gap. It is normal on renovation jobs. It becomes a problem only when you cannot see it coming.
Track it in three places:
-
The deposit payment, dated and tied to the job
-
The expected draw or billing date
-
The running balance of what you have paid versus what you have been paid
If the deposit is paid by card, record any card fee as its own small cost so it does not get buried in the job total. If it comes from checking, record the check number.
On bank-funded jobs, the draw timing is set by the inspector and the lender, not by you. Your records need to support each draw request line by line, which is one more reason to match invoices to the budget early.
A CPA should confirm when deposits and billings count as income for your business, since the rules depend on your circumstances.
For a practical way to plan around payment timing, see our construction cash flow forecast guide.
Renovation Budget vs Actual by Job Type
Budget vs actual means comparing what you planned to spend on each line with what you actually spent. Do it by job type, because a kitchen and a full gut do not go over budget in the same places.
| Job Type | Budget Line | Actual Line | What to Check |
|---|---|---|---|
| Kitchen rehab | Cabinets, counters | Sub invoices | Allowance overruns |
| Full gut | HVAC, sheetrock | Sub invoices | Extra duct runs |
| Bath remodel | Plumbing, tile | Sub invoices | Change in scope |
| Whole home | All trades | All invoices | Phase timing |
This table is a template, not a set of numbers. Fill it from your own jobs.
If a line such as HVAC runs consistently comes in over the quote, the next quote for that work may need room for hidden conditions. Run the comparison when the job closes, not at year end, while the details are still fresh.
Billing by Completed Items and Supporting Each Line
Many renovation owners bill the homeowner as items are completed rather than on a fixed percentage schedule. That usually means demo, cabinets, sheetrock, paint, and HVAC as separate billing points. For percentage-based billing and retainage, see our guide to progress billing and retainage.
Each billed item needs a backup document:
-
Demo: photos and the sub's invoice
-
Cabinets: supplier invoice and delivery record
-
Sheetrock: sub invoice and completion note
-
Paint: sub invoice and walkthrough sign-off
-
HVAC: equipment invoice, duct invoice, and warranty paperwork
When you bill by completed items, the homeowner or draw inspector can match each line to visible work. That speeds approval and reduces disputes.
Watch out: billing an item before its support is filed invites a rejection and a delayed draw.
A clear accounts payable routine keeps sub bills, approvals, and job costs in one place. Our guide to construction accounts payable walks through one.
Recording Homeowner Payments in QuickBooks
Homeowners often pay a larger deposit up front and smaller amounts as items are completed. Money received before the work is done is generally a customer deposit, a liability, until you earn it. It should not sit in income yet.
A clean pattern looks like this:
-
Record the deposit against the homeowner's job as a customer deposit
-
Invoice each completed item to the same job
-
Apply the deposit to those invoices as the work is done
-
Code every sub cost to the same job
When everything carries the same job, the job report shows money in, money out, and what is still owed.
A CPA should confirm how deposits and billings are treated for tax and revenue timing in your situation. An attorney should review lien waivers and Texas payment rules before you rely on either.
File the Invoice, Estimate, and Warranty With the Project
File the sub's invoice, the handwritten estimate, and the warranty paperwork together in the project folder. Give the homeowner a copy of the warranty with its end date written on it.
The end date matters because, under the terms of your contract, repairs after the warranty ends are typically the homeowner's cost. A homeowner who has the date in hand is far less likely to call years later expecting covered work. A homeowner who never got the paperwork may argue. Have an attorney confirm your warranty language.
The project folder should hold:
-
The itemized quote
-
The handwritten estimate, if one exists
-
Every sub invoice
-
The warranty document with its end date
-
Photos of completed work
One folder, one job, start to finish. When a dispute or a tax question comes up, everything is in one place.
Frequently Asked Questions
How do you calculate subcontractor costs for a renovation?
Start with the sub's itemized quote, not a lump sum. For an HVAC replacement, that means equipment plus a stated cost per duct run, so you can check the invoice line by line. Add the quote to the job budget, record the sub's invoice against the same job in QuickBooks, and compare the final invoice to the quote. Get any scope change in writing before the work happens so the number you track matches the number you pay.
How should a contractor compare budgeted and actual costs on a renovation?
Set the budget by line item before work starts, then post every sub invoice and receipt to the matching line. Show each trade, such as demo, cabinets, sheetrock, paint, and HVAC, with the budgeted amount beside what was actually spent. Review it after each draw or billing cycle, not at the end of the job, so a variance is still something you can act on.
How do you record a homeowner payment received before renovation work is complete?
Record it as a customer deposit, a liability, tied to that homeowner's job, then apply it to invoices as items are completed. A CPA should confirm when deposits and billings count as income for your business, because the treatment affects both your books and your tax return.
What documents should you keep for a renovation subcontractor?
Keep the sub's invoice, the original estimate, and the warranty paperwork together in the project file, and give the homeowner a copy of the warranty with its end date. Have an attorney review lien waivers and Texas payment rules, and keep signed waivers in the same file so the paper trail supports both your job records and any dispute later.